1st day: ground checks: external surfaces, bays and cabin visual inspection, static aircraft system and cockpit checks, engine tests.
2nd day: acceptance flight: checks during flight of all aircraft systems (including cabin systems) and aircraft behaviour in the whole flight envelope.
3rd day: physical rework or provision of solutions for all technical and quality snags open in delivery.
4th day: completion of technical acceptance. Technical closure of the aircraft and all associated documents attesting the aircraft’s compliance to the type certificate and conformity to the technical specification allowing the issuance of the Certificate of Airworthiness.
5th day: transfer of the aircraft's title deeds to the customer airline: the aircraft changes owner. Preparation of the aircraft for the ferry flight to its home base.